The African Aid Foundation aims to build mosques in Malawi to provide places for prayer, and to establish schools that teach the Qur’an and religious studies in general.
For the population, women and children in particular.
The mosque is used for teaching converts about their religion, and it is a reference in religious and worldly matters.
It is used as a base for literacy and reading and writing activities, as well as in awareness campaigns.
Health and environment, vocational training and income-generating projects.
The total area of the mosque is 390 m².
Construction of brick and cement and concrete roof
Foundation: Excavation is carried out to a maximum depth of 1.5 m from the floor foundation level or until the rock and foundation are reached.
It consists of armed bases with an average base area of 1.4 * 1.2 and a depth of 40 cm before implementation.
Reinforced foundations: 10 cm of clean brush is applied to the wall base and the bottom of the foundations.
Secondly, the columns: 37 columns will be implemented for the entire area of the mosque, with dimensions of 40*25 cm for the external columns and 40
Poison for internal columns with Phi 16 reinforcement
Walls: The walls are built with blocks, with a wall width of 20 cm.
Implementation of the concrete slab from reinforced concrete with Y12 reinforcement, 16-meter beam, and 25-meter width
cm and a depth of not less than 40 cm
Finishing: Plastering: The entire mosque will be plastered inside and out according to the agreed-upon proportion.
Ceramic tiles for the entire project flooring, size 40cm*40cm used
Turn off the electricity, making sure that the plug is placed only in the microphone location, and that a light is placed in each panel.
Build a lighthouse no less than 8 meters high.
Rainbow paints are applied on three coats.
The windows are made of aluminum, with the window size being 1.5 x 1.5 cm wide.
The total area of the mosque is 100 m²
The area of the men’s prayer room is (5m * 9m) total (45m²).
The area of the women’s prayer room is (5m * 9m) total (45m²).
With two bathrooms and an ablution area of 10 square meters
Construction of brick and cement and zinc roof
Foundation: The footing is made of 10 cm thick concrete on the floor of the excavation bottom.
The construction is done using solid clay bricks with a wall thickness of 13 cm and a foundation height of not less than 80 cm depending on the soil type and slope.
All necessary measures are taken to prevent harmful insects and the damage they cause to the safety of the facility in the long term by using medication and chemicals in the base layer.
Backfilling and leveling: The foundation is backfilled, leveled, and a strong replacement soil is created and compacted well.
Make a concrete floor (slab) over the replacement soil with a thickness of 10 cm and use the insecticide again.
Structural structure: The room walls are built from solid clay bricks, with a wall thickness of 9 cm, up to the upper level of the window.
The waist is made of reinforced concrete with a thickness of 20 cm around the entire room. It is used for its structural importance in transferring and distributing loads, connecting walls, providing the necessary support and balance, and as a threshold for doors and windows.
The average building height is approximately 3.8 m.
Ceiling: Mosky wood is used to make the ceiling gables using (Pin Wood- hard wood).
Wood insulation using a type of paint (Solignum) that resists wood corrosion and protects it from moisture and heat.
Covering is done using zinc sheets.
Tests are conducted to ensure that there are no leaks and to check the slope of rainwater drainage.
Finishing: The entire room is covered with white plaster, with a mixture of white plaster and painting on the outside of the block.
Interior and exterior painting is done using oil paint or sealer in the case of painting using Rainbow paint.
Doors and windows are installed with an internal security frame, glass is installed, and window handles are installed to close and open the windows.
The total area of the mosque is 80 m²
The area of the men’s prayer room is (5m * 7m) total (35m²).
The area of the women’s prayer room (5m * 7m) total (35m²).
With two bathrooms and an ablution area of 10 square meters
Construction of brick and cement and zinc roof
Foundation: The footing is made of 10 cm thick concrete on the floor of the excavation bottom.
The construction is done using solid clay bricks with a wall thickness of 13 cm and a foundation height of not less than 80 cm depending on the soil type and slope.
All necessary measures are taken to prevent harmful insects and the damage they cause to the safety of the facility in the long term by using medication and chemicals in the base layer.
Backfilling and leveling: The foundation is backfilled, leveled, and a strong replacement soil is created and compacted well.
Make a concrete floor (slab) over the replacement soil with a thickness of 10 cm and use the insecticide again.
Structural structure: The room walls are built from solid clay bricks, with a wall thickness of 9 cm, up to the upper level of the window.
The waist is made of reinforced concrete with a thickness of 20 cm around the entire room. It is used for its structural importance in transferring and distributing loads, connecting walls, providing the necessary support and balance, and as a threshold for doors and windows.
The average building height is approximately 3.8 m.
Ceiling: Mosky wood is used to make the ceiling gables using (Pin Wood- hard wood).
Wood insulation using a type of paint (Solignum) that resists wood corrosion and protects it from moisture and heat.
Covering is done using zinc sheets.
Tests are conducted to ensure that there are no leaks and to check the slope of rainwater drainage.
Finishing: The entire room is covered with white plaster, with a mixture of white plaster and painting on the outside of the block.
Interior and exterior painting is done using oil paint or sealer in the case of painting using Rainbow paint.
Doors and windows are installed with an internal security frame, glass is installed, and window handles are installed to close and open the windows.
The total area of the mosque is 70 m².
The area of the men’s prayer room is (5m * 6m) total (30m²).
The area of the women’s prayer room (5m * 6m) total (30m²).
With two bathrooms and an ablution area of 10 square meters
Construction of brick and cement and zinc roof
Foundation: The footing is made of 10 cm thick concrete on the floor of the excavation bottom.
The construction is done using solid clay bricks with a wall thickness of 13 cm and a foundation height of not less than 80 cm depending on the soil type and slope.
All necessary measures are taken to prevent harmful insects and the damage they cause to the safety of the facility in the long term by using medication and chemicals in the base layer.
Backfilling and leveling: The foundation is backfilled, leveled, and a strong replacement soil is created and compacted well.
Make a concrete floor (slab) over the replacement soil with a thickness of 10 cm and use the insecticide again.
Structural structure: The room walls are built from solid clay bricks, with a wall thickness of 9 cm, up to the upper level of the window.
The waist is made of reinforced concrete with a thickness of 20 cm around the entire room. It is used for its structural importance in transferring and distributing loads, connecting walls, providing the necessary support and balance, and as a threshold for doors and windows.
The average building height is approximately 3.8 m.
Ceiling: Mosky wood is used to make the ceiling gables using (Pin Wood- hard wood).
Wood insulation using a type of paint (Solignum) that resists wood corrosion and protects it from moisture and heat.
Covering is done using zinc sheets.
Tests are conducted to ensure that there are no leaks and to check the slope of rainwater drainage.
Finishing: The entire room is covered with white plaster, with a mixture of white plaster and painting on the outside of the block.
Interior and exterior painting is done using oil paint or sealer in the case of painting using Rainbow paint.
Doors and windows are installed with an internal security frame, glass is installed, and window handles are installed to close and open the windows.
The total area of the mosque is 60 m².
The area of the men’s prayer room is (7m * 7m) total (49m²).
With two bathrooms and an ablution room with an area of 11 square meters
Construction of brick and cement and zinc roof
Foundation: The footing is made of 10 cm thick concrete on the floor of the excavation bottom.
The construction is done using solid clay bricks with a wall thickness of 13 cm and a foundation height of not less than 80 cm depending on the soil type and slope.
All necessary measures are taken to prevent harmful insects and the damage they cause to the safety of the facility in the long term by using medication and chemicals in the base layer.
Backfilling and leveling: The foundation is backfilled, leveled, and a strong replacement soil is created and compacted well.
Make a concrete floor (slab) over the replacement soil with a thickness of 10 cm and use the insecticide again.
Structural structure: The room walls are built from solid clay bricks, with a wall thickness of 9 cm, up to the upper level of the window.
The waist is made of reinforced concrete with a thickness of 20 cm around the entire room. It is used for its structural importance in transferring and distributing loads, connecting walls, providing the necessary support and balance, and as a threshold for doors and windows.
The average building height is approximately 3.8 m.
Ceiling: Mosky wood is used to make the ceiling gables using (Pin Wood- hard wood).
Wood insulation using a type of paint (Solignum) that resists wood corrosion and protects it from moisture and heat.
Covering is done using zinc sheets.
Tests are conducted to ensure that there are no leaks and to check the slope of rainwater drainage.
Finishing: The entire room is covered with white plaster, with a mixture of white plaster and painting on the outside of the block.
Interior and exterior painting is done using oil paint or sealer in the case of painting using Rainbow paint.
Doors and windows are installed with an internal security frame, glass is installed, and window handles are installed to close and open the windows.